Inspection Library

Cladding render brickwork

Cladding fixed over out-of-plumb, bowed, or structurally compromised wall framing

3 examples in 3 videos 2 major 1 minor

What it is

The composite cladding panels are visibly tilted and deviate out of plumb by up to 27 millimetres over a one-metre span. This substantial misalignment indicates defective framing alignment and will prevent compliant installation of subsequent external finishes.

Window reveals lack proper finishes and sarking does not terminate correctly, exposing interior plasterboard and frame timber to moisture. Coarse drywall screws shattered timber studs and panels pull off freely by hand.

Cladding was fastened directly to an unstraightened timber frame without cavity battens, resulting in wall bowing and alignment deviations of up to 10 mm. This poor installation leaves visible gaps and distorts the facade.

Standards

Explained in our own words. Check the current edition; which edition applies depends on the building permit date.

Also relevant to

Structural framing