Inspection Library

Fire safety smoke alarms

Defective Firestop, Penetration, and Joint Sealing

4 examples in 2 videos 4 major

What it is

A structural beam penetrating through the dividing fire separation wall to the adjacent unit was improperly sealed using plaster adhesive instead of an approved fire-rated penetration system. In addition, an engineered structural bracket is omitted.

Firestop sealant between adjoining townhouses was terminated prematurely rather than installed continuously along the joint. Furthermore, the mandatory 20 mm clearance to fire panels is non-compliant and inconsistent.

An additional required 16 mm protective firestop layer was omitted at the cantilevered partition section. In addition, the necessary 20 to 40 mm expansion clearance was reduced to only 4 to 6 mm in multiple locations.

Standards

Explained in our own words. Check the current edition; which edition applies depends on the building permit date.

Also relevant to

Structural framing

Video examples