Foreign materials or unremoved formwork in concrete placement
What it is
Inspection via borescope identified waste plaster and raw timber chipboard left inside an unsealed slab penetration. Any pooling water or moisture would seep into the cavity and degrade the timber and subfloor materials.
Concrete flatwork was poured directly against or over timber formwork that remains embedded in the ground rather than stripped. This improper placement leaves uncompacted edges prone to rot, pest ingress, and structural subsidence.
Standards
- AS 2870 Suggested reference, unverified
- AS/NZS 3600 Suggested reference, unverified
Explained in our own words. Check the current edition; which edition applies depends on the building permit date.
Also relevant to
Finishes painting tilingSite works landscaping
Video examples
- They Tried to Silence Us 43:57 minorPlaster and combustible chipboard abandoned in slab penetration
- Paid in Full, Yet Scammed? Unearthing a $1M NSW Building Nightmare! 15:04 minorSubstandard concrete placement over unremoved timber formwork