What it is

Concrete is being poured for a pavement or driveway without bar chairs to support the steel reinforcement mesh. Lifting reinforcement manually during pouring is non-compliant and causes the steel to sink back down when stepped on, leading to inadequate cover and cracking risk.

The plastic bar chairs supporting the reinforcing mesh were spaced approximately 1200 mm apart. This exceeds the maximum allowable spacing of 800 mm, risking sagging and insufficient concrete cover.

Concrete was poured over reinforcement steel across multiple sections, including the rear units and front porch area, without bar chairs. The inspector notes this fails to maintain the mandatory maximum support spacing required by building codes.