Undersized and Non-Compliant Pad Footings
What it is
Verification by excavation revealed the entry post concrete footings failed to reach the specified depth of 600 mm. The certified engineer passed the shallow footings without proper on-site verification.
Pad footings supporting steel structural columns were cast undersized at 400 mm by 400 mm instead of the engineered 500 mm by 500 mm by 600 mm deep design. The columns lack the required 20 mm non-shrink grout bed, 75 mm concrete encasement, and contain plastic window packers under the base plates.
Ground-penetrating radar scanning verified that the concrete pad footings supporting the chimney columns are only approximately 400 mm deep rather than 600 mm deep. The concrete was placed with complete omission of the SL82 top and bottom reinforcement specified by the structural engineer.
Standards
- AS 2870 Suggested reference, unverified
Explained in our own words. Check the current edition; which edition applies depends on the building permit date.
Also relevant to
Video examples
- They Approved THIS?! Engineer Caught in Major Mistake! 19:33 majorUndersized depth on entry post P1 footings
- I inspected a $500K Dangerous Extension 20:53 majorSubfloor pad footings undersized and missing specified grout and encasement
- I inspected a $500K Dangerous Extension 26:02 majorOmission of steel reinforcing mesh and shallow depth in structural pad footings