Flooring substrate fixing and framing defects
What it is
A structural timber member splice is placed too close to its anchorage point, failing minimum distance rules. Additionally, the joist hanger bracket is inadequately secured with missing fasteners and lacks required tie-down strapping.
Flooring panels have been incorrectly secured to posi-strut floor joists using nails instead of mechanical screws. In addition, the posi-struts are undersized at 260 mm width instead of the required 300 mm width.
A structural bracket or component is installed upside down contrary to engineering plans. Additionally, an unsuitable, non-compliant piece of timber was improvised to reinforce a compromised joist penetration.
Standards
- AS 1684 Said in videoSuggested reference, unverified
- AS 1684.2 Suggested reference, unverified
- AS 1860.2 Suggested reference, unverified
Explained in our own words. Check the current edition; which edition applies depends on the building permit date.
Also relevant to
Video examples
- $7 Million Build Nightmare | Engineering Plan Error… 8:48 majorInadequate structural timber framing splice clearance and joist fixings
- Are Homebuyers Getting Scammed…We Returned to the $2M Disaster 1:42 majorFlooring fixed with nails and undersized posi-struts
- Are Homebuyers Getting Scammed…We Returned to the $2M Disaster 12:26 majorStructural element installed inverted and non-conforming joist brace
- Are Homebuyers Getting Scammed…We Returned to the $2M Disaster 18:34 majorParticleboard flooring secured with nails to steel framing
- Home Inspection Disaster: Marong's Shemozzel Brickwork… 12:41 majorUnfixed particleboard flooring substrate