Structural framing

Posi-strut joist damage, modification, and support defects

6 examples in 3 videos 6 major

What it is

Floor posi-struts have suffered physical damage and crushing during installation. Gaps of roughly 30 mm exist under structural supports, causing noticeable structural movement across the floor frame.

Posi-strut joist FT34 was installed off-location onto an ad-hoc builder-constructed nib wall instead of the engineered frame layout. The joist also features an unauthorized cantilevered overhang.

The end of a manufactured posi-strut joist was cut, field-modified, and heavily nailed with dozens of fixings. This unauthorised alteration split the timber chord and compromised the joist's engineered structural capacity.