Box gutter connection, fastening, and joint sealing defects
What it is
The connection between the box gutter and the rainhead lacks a mechanical lap seam and relies purely on a bead of silicone. Thermal expansion and contraction will rupture the sealant and admit water behind the external cladding.
Metal apron and box gutter flashings were installed without continuous silicone sealant along laps, leaving wide 100 mm unbonded voids where 40 mm maximum spacing is mandated. Fasteners are under-rated Class 2 instead of external Class 3.
A roof box gutter was terminated into a rainhead without mechanical fixings. Omitting mechanical fasteners creates a loose junction prone to displacement and storm water leakage.
Standards
- AS 3566.2 Suggested reference, unverified
- AS/NZS 3500.3 Suggested reference, unverified
- HB 39 Suggested reference, unverified
Explained in our own words. Check the current edition; which edition applies depends on the building permit date.
Also relevant to
Video examples
- Builder LOSES IT During Inspection – Crazy Confrontation! 23:26 majorUnsealed gutter junction relying entirely on surface silicone
- Worst Builder 2024’s Next Victim 43:00 majorBox gutter flashing joints open without sealant and excessive fastener gap
- I Inspected Her Brand New Home… It’s Worse Than It Looks 12:28 minorBox gutter not mechanically fastened to rainhead